Project Experience

Gas Processing Facilities

Gas Processing Facilities – Domestic
PROJECT: Septimus Sour Gas Plant Phase 1 – 20 MMSCFD, & Expansion to 40 MMSCFD
COMPANY: Crew Energy Inc.
LOCATION: Fort St. John, BC
Acero was responsible for the engineering, procurement and construction management of a 20 MMSCFD sour gas inlet refrigeration and LPG extraction plant, and expansion to handle 40 MMSCFD.  Scope of work included up front scoping support, including assessment of best location for plant placement, FEED and detailed design. Detailed deliverables including (but not limited to) costing and controls, planning (scheduling), 3D model and associated outputs, E&I drawings, and I&C control schematics.costing and controls, planning (scheduling), logistics.

PROJECT:  Gas Plant Debottleneck and Expansion FEED and Detailed Engineering
COMPANY: Painted Pony Energy Ltd.
LOCATION: Fort St. John, BC
Acero’s scope of work included compressor installation to expand compression from 28 MMSCFD to 40 MMSCFD, flare system upgrade without taking the existing system offline, power generation expansion, coalescing filter installation, fuel gas measurement system, and regulatory support.

PROJECT: B-24-H Sour Gas Plant Debottleneck and Expansion FEED and Detailed Engineering
COMPANY: Confidential Client
LOCATION: Fort St. John, BC
Acero’s scope of work was to add an additional 40MMSCFD train in parallel with an existing 20 MMSCFD raw gas facility.  Facility improvements included slug catcher, relocation and use of an available separator as FKOD for acid gas going to incinerator, evaluation and upgrade of gas power/ generator units to accommodate winter consumption (mainly heat tracing); associated instrumentation and control upgrades and accommodations.

PROJECT: Progress Venturi VRU
COMPANY: Confidential Client
LOCATION: Pouce, AB
Acero was responsible for the engineering, design, procurement and schedule of flare and VRU system revamp. Acero had already completed a capacity study to help plan for potential upgrades including the evaluation of all primary process equipment. Engineering assessments were completed for an estimate of fuel gas consumption, instrument air consumption, flare gas usage and as well, some blockage issues (resulting in thief hatch releases at the tank farm). Purge gas and venturi system designs were merged to minimise wasted gas (by conserving during tank out-breathing) and resolve thief hatch issues by providing positive gas during in-breathing.

PROJECT: McMahon Gas Plant Amine Still Replacement
COMPANY: Confidential Client
LOCATION: NE BC
Acero’s scope of work included the FEED, detailed engineering, and procurement for the replacement of an Amine Still (column #3) with an in-kind replacement, but constructed of 316L stainless steel materials, at the Enbridge McMahon Gas Plant.

Gas Processing Facilities – International
PROJECT: Badila Gas Injection
COMPANY: PCM, a Glencore Company
LOCATION: Chad, Africa
Acero was responsible for the detailed engineering and design, project controls, and technical support for all procurement activities for a gas injection facility capable of injecting 12MMSCFD of gas at 1,500 psig.

PROJECT: Kurdamir Block Development
COMPANY: Confidential Client
LOCATION: Kurdistan, Iraq
Acero was responsible for a conceptual study for the development of the Kurdamir Block (Greenfield) in Kurdistan, Iraq. Scope of work included the conceptual study for 50,000 BOPD CPF and 300 MMSCFD gas plant c/w sulphur recovery, project scheduling and TIC estimate.

PROJECT: Amguri Interim Condensate Recovery
COMPANY: Canoro Resources Ltd.
LOCATION: Assam, India
Acero was responsible for the detailed engineering and design, procurement and logistics, and construction management of a brownfield, 20 MMSCFD gas inlet / 1500 bpd condensate recovery project in remote, northeast India. With the reservoir in  “retrograde condensation” (ie. liquids being permanently lost in the reservoir due to depressurisation causing an in-situ gas to liquid phase change), the project was fast-tracked and interim condensate removal was installed

 

Compressor Stations

PROJECT: Wilrich 16-27 Compressor Station Expansion FEED and Detailed Engineering
COMPANY: Confidential Client
LOCATION: Central AB
Acero was responsible for expanding the Wilrich compressor station with a historic throughput of 22 MMSCFD of raw gas and condensate.  The expansion was with a 48 MMSCFD train, parallel to the existing 22 MMSCFD facility; resulting in a total plant throughput capacity of 60 MMSCFD.  Other facility upgrades included 3 phase inlet separators, dehydrator, new MCC building, upgrade of existing incinerator burner, one new high pressure flare stack, one new flare knockout drum were also incorporated.

PROJECT: Daiber Compressor Station
COMPANY: Painted Pony Energy Inc.
LOCATION: Fort St. John, BC
Acero’s scope of work included the engineering, design and regulatory support of a new compressor/dehydration facility designed for 50 MMSCFD of high press production and 25 MMSCFD of lower pressure compression.  Water storage, power generation and sales gas metering was also required.

PROJECT: Gas Plant Debottleneck and Expansion
COMPANY: Painted Pony Energy Inc.
LOCATION:  Fort St. John, BC
Acero was responsible for the FEED, detailed engineering and regulatory support of a compression expansion from 28 MMSCFD to 40 MMSCFD.  Other facility upgrades included flare system upgrade, power generation including generator installation, and fuel gas measurement.

PROJECT: Pine Creek Compressor Station FEED
COMPANY: Confidential Client
LOCATION: Edson, AB
Acero’s scope of work included the engineering, procurement, and construction support of a green-field compressor station designed for 10 MMSCFD throughput of sour gas.

PROJECT: Pine Creek Compressor Station FEED
COMPANY: Confidential Client
LOCATION: Edson, AB
Acero was responsible for the engineering, design and procurement of a compressor station in order to process the production of new sour wells. Plant capacity designed to handle 20-25 MMSCFD of gas with a maximum liquid yield of 100bbl/MMSCFD.

Pump Stations

Pump Stations – Domestic
PROJECT: Booster Pump Installation
COMPANY: Pengrowth Energy Corp.
LOCATION: Judy Creek, AB
Acero was responsible for the detailed engineering and design, procurement of main equipment and construction support of a pump station in central Alberta.  The project featured two 750 HP pumps and housings to provide water injection capacity of 16,000 m3/d at 14,900 kPag.

PROJECT: Asset Circuitization Support
COMPANY: Confidential Client
LOCATION: Various
Acero’s scope of work was to inspect 70 sites (including several pump stations) and identify the circuitization loops and asset verification to assure integrity and safety.  Each site examined required tailoring of the inspection scrutiny based on operating conditions.

Pump Stations – International
PROJECT: Crude Oil Topping Unit
COMPANY: Griffiths, a Glencore Company
LOCATION: Chad, Africa
Acero was responsible for the conceptual study to evaluate the feasibility of installing crude oil topping at the initial pumping station of a 16” 520 km pipeline. Pipeline hydraulic simulations were also provided to analyze options for pump and heating stations, variations in MAOP, production capacities, pipeline sizes, based on crude oil assay and temperature.

Conventional Oil Facilities

Conventional Oil Facilites – Domestic
PROJECT: Gilby Central Oil Battery (FEED & Detailed Engineering)
COMPANY: Confidential Client
LOCATION: Central AB
Project featured the detailed engineering and design of a new central oil battery to handle 4,000 BBL/D of light oil, and 5 MMSCFD of gas.

PROJECT: Gilby Oil Battery Debottlenecking Pre-FEED
COMPANY: Confidential Client
LOCATION: Central AB
Acero was responsible for determining the feasibility of developing a central multi-well processing oil battery for 2 production capacity options (25000 bbl/d & 4000 bbl/d) at a new Gilby pilot production facility versus debottleneck of an existing facility.

PROJECT: Alderson Oil Batteries
COMPANY: Crew Energy
LOCATION: Southern AB
Acero was responsible for the design and regulatory support, procurement and construction of several oil batteries and expansions in the Alderson Field.

PROJECT: Garrington Glycol Dehy Installation
COMPANY: Pengrowth Energy Corp.
LOCATION: Southern AB
Acero was responsible for the process sizing, selection, and integration of a Glycol Dehy into an existing facility to allow for increased production through the battery, and onward, to a new third party producer. El&C design was also required to upgrade the existing MCC, as well as a technical review of vendor design and documentation.

PROJECT: Carson Creek Tank Installations
COMPANY: Pengrowth Energy Corp.
LOCATION: Carson Creek, AB
Project featured the detailed tank and foundation design and process review, procurement support of a 15,000 bbl produced water storage tank, and 10” flare installation to accommodate increased volume from the field.

Conventional Oil Facilities – International
PROJECT: Acordionero CPF Expansion
COMPANY: Gran Tierra Energy Inc.
LOCATION: Middle Magdalena Basin, Colombia
Since 2017, Acero has been responsible for several projects; Pre-FEED through detailed design, related to the expansion of an existing early production facility (EPF) into a central processing facility (CPF) in the Acordionero field in Colombia. The facility was expanded to handle larger volumes of produced liquids; from 3500 BOPD to 7500 BOPD.

  • CPF expansion phase 1 – from 3,500 BOPD to 7,500 BOPD (Pre-FEED through detailed design including procurement support)
  • CPF expansion phase 2 – 15,000 BOPD (FEED, procurement & detailed design support) 
  • CPF expansion phase 3 – 25,000 BOPD (Debottlenecking study)

PROJECT: 40,000 BOPD Operation & Maintenance Support Facility
COMPANY: Confidential Client
LOCATION: Al-Basrah, Iraq
Acero was responsible for the front end conceptual engineering through to detailed design of a 40,000 bopd operation and maintenance support facility in the Zubair oilfield of southern Iraq.  Scope of work also included procurement, and coordination of inspection and logistics of major equipment. 

PROJECT: Bretana Development
COMPANY: Gran Tierra Energy Inc.
LOCATION: Loreto, Peru
Acero was responsible for providing technical direction to the EPC contractor for a 20,000 bpd EPF, completing PFDs and P&IDs for a 2,500 bpd EPF, project management consulting and reviewing all major deliverables.
Well production for 18.6 degree API oil produced naturally, then moved to jet pump artificial lift system sized for a capacity of 4,000 BPD of total fluids. Produced fluids driven by the jet pump were directed to a two phase separator in order to remove associated gas which was sent to a flare, while production water was designed to be stored in tanks. Production was either transported on barges or injected into a sump pit

Water Injection Facilities

Water Injection – Domestic
PROJECT: Water Injection Facility & Pipeline
COMPANY: Pengrowth Energy Corp.
LOCATION: Judy Creek, AB
Acero was responsible for the detailed engineering, design, procurement, regulatory support and construction management of a water injection facility and pipeline in Judy Creek, Alberta.  The project featured the installation of two salt water injection pipelines, facility piping, including pipeline tie-ins (as well as design considerations for future tie-ins), horizontal filter selection, pump design, line pipe design and selection.

PROJECT: Water Disposal Facility
COMPANY: Confidential Client
LOCATION: Peace River, AB
Acero was responsible for the detailed engineering, design, procurement and construction management of the expansion of an existing oil battery to incorporate water handling and disposal capability at the site.  The project featured new (fiberspar) pipelines to gather water from other batteries, and to deliver produced water to nearby disposal wells.  Facility work included the design and installation of three 2000 bbl water tanks, and various water transfer/skim oil/disposal pumps.

PROJECT: Parkland Water Injection
COMPANY: Confidential Client
LOCATION: Fort St. John, BC
Acero was responsible for the detailed design and procurement for a water disposal facility at the Parkland Gas Plant, capable of handling 300 m3/d, with the ability to expand to 600 m3/d in the future.  A new injection pump skid, condensate tank and pipeline will be installed as part of the project.

Water Injection – International
PROJECT: Acordionero Water Injection Facility
COMPANY: Gran Tierra Energy Inc.
LOCATION: San Martin, Colombia
Acero was responsible for providing a conceptual design for the expansion of the Acordionero central processing facility (CPF) to include produced water treatment and injection equipment. The new water handling facility was designed for a throughput capacity of 39,000 BWPD complete with necessary high pressure pipeline to inject through six (6) nearby injection wells each with two zones.

PROJECT: Badila CPF Water Injection Project
COMPANY: PCM, a Glencore Company
LOCATION: Chad, Africa
Acero was responsible for Pre-FEED and FEED  for a water treatment and injection facility over two phases (35,000 BWPD & 65,000 BWPD) by installing CPI, skimming tanks, booster pumps, filters and high pressure injection facility complete with a high pressure water injection network.  Scope of work also included an 8 MW gas to power generation facility, required to service the facilities increased power demand.

CLICK HERE TO DOWNLOAD our Water Handling Highlights Brochure

Oil Storage Facilities

Oil Storage Facilities – Domestic
PROJECT: Tank Replacements
COMPANY: Pengrowth Energy Corp.
LOCATION: Judy Creek, AB
Project featured the replacement of an existing 10,000 BBL shipping tank with 3,000 BBL tank, replacement of 3,000 BBL water tank with 2,000 BBL tank, on-site jack-n-roll relocation and refurbishment of 10,000 BBL produced water storage tank (including foundation design and roof replacement), and construction planning and schedule control.

PROJECT: Carson Creek Tank Installations
COMPANY: Pengrowth Energy Corp.
LOCATION: Carson Creek, AB
Project featured the detailed tank and foundation design and process review, procurement support of a 15,000 bbl produced water storage tank, and 10” flare installation to accommodate increased volume from tank.

Oil Storage Facilities – International
PROJECT: PCT Blending & Export Terminal Expansion
COMPANY: PCM, a Glencore Company
LOCATION: Chad, Africa
Acero was responsible for increasing capacity of the PetroChad Transportation Company (PCT) blending and export terminal from a rate of 35,000 bpd to 75,000 bpd in Chad, Africa.  Facility required installation of three 17,5000 bbl storage tanks c/w heating capabilities and transfer/recycle pumps, electrical building, and chemical injection packages.

Pipeline Projects

Pipeline Projects – Domestic
PROJECT: Pipeline Project
COMPANY: Polar Star Oil and Gas Inc.
LOCATION: Laprise Creek, BC
Acero’s scope of work included the engineering and design, procurement, and regulatory support for a 10”, 12km main trunk line with 4” parallel common ditch fuel gas pipeline, as part of a new gathering system.  Crossing considerations included 7 open-cut road allowances, 18 stream crossings (3 of which were bored), and 4 archaeological no-work zones, which were bored.

PROJECT: Gas Pipeline Replacements
COMPANY: Pengrowth Energy Corp.
LOCATION: Swan Hills, AB
Acero’s scope of work included the detailed design and procurement of multiple 4”to 12” LP & HP gas pipeline replacements (externally coated steel as well as free standing liner composite pipelines).  Projects featured a new pipeline separator (96” OD x 20’ S/S), surface piping, instrumentation and controls, pig launching and receiving facilities, major road and water crossings

PROJECT: Pipeline Network Modeling
COMPANY: Pengrowth Energy Corp.
LOCATION: Irricana, AB
Project featured a Pipe-Flo model for the existing wells and pipelines in the Irricana area to evaluate the existing network, simulate options for the re-routing of production, and to bring low producing shut-in wells back online. Network contained 20 wells, 42 pipeline segments, and 1 booster compressor.

Pipeline Projects – International
PROJECT: Doseo Pipeline project FEED
COMPANY: Confidential Client
LOCATION: Chad, Africa
Scope of work consisted of cost estimating to support alternative configurations and options, development of temperature gradient monitoring, feasibility assessment of on-shore barge equipment, and development of estimating TIC template.

CLICK HERE TO DOWNLOAD our Pipeline Highlights Brochure

Pipeline Integrity Support

Pipeline Integrity Support Projects – International

PROJECT: Pipeline Integrity – Repairs, Sectional Replacements, and Rerouting
COMPANY: Confidential Client
LOCATION: Various

  • Scope of work included the engineering and assessment of several temporary & permanent sleeve repairs between 8” – 22” designed to fit directly on pipe or with an elevated collar (dependent on severity of wrinkle).  Typical deliverables have included, repair drawings, Finite Element Analysis, fatigue analysis, and final report.
  • Acero provided several design packages for partial pipeline replacements including rail, road and water body crossings.  Typical scope has included stress analysis, pipeline & riser details, bend specification & schedule and alignment sheets.

Power Generation

Power Generation – Domestic
PROJECT: Power Generation
COMPANY: Confidential Client
LOCATION: Central AB
Acero provided full engineering services for the scoping, design, procurement and installation of (currently) 16 MW of power (at five locations) so as to significantly reduce reliance on utility power costs while at the same time, taking advantage of available (cheap) fuel gas.

PROJECT: Power Generation
COMPANY: Confidential Client
LOCATION: Swan Hills, AB
Acero was responsible for evaluating two power generation scenarios for power generation with the option to sell excess power to the grid in the future.  Scope of work included feasibility and design, regulatory support, and construction and commissioning support.

Power Generation – International
PROJECT: Mangara Power Generation and Generation to Well Site FEED
COMPANY: PCM, a Glencore Company
LOCATION: Chad, Africa
Acero was responsible for completing a FEED study for the power generation (6 MW), sub-station and transmission line requirements to supply power to a minimum of 20 well sites with provision to expand to 50 well sites.  Scope of work included a technology optimization study, technical safety review and big evaluations and recommendations.

PROJECT: Acordionero Power Generation and Distribution Pre-FEED
COMPANY: Gran Tierra Energy Inc.
LOCATION: San Martin, Colombia
Acero was responsible for a pre-FEED study to build a 15 MW central power generating facility located at the Acordionero CPF. The intent of the generation facility was to supply power to the CPF, water injection facility, truck loading and six (6) well pads via a transmission network. 

Specifications

PROJECT: Specification Development for E&P Facilities & Pipelines
COMPANY: Various
Acero has developed & implemented in-house mechanical specifications for Domestic and International energy companies.
A sample of some of the specifications that Acero has written include:

EQUIPMENT SPECIFICATIONS
• API 610 centrifugal pumps
• ASME B73.1 general sour horizontal centrifugal pumps
• Positive displacement/reciprocating pumps
• Direct and indirect fired heaters
• Heat medium package
• Pressure vessels and heat exchangers
• Above ground knock out drums

EI&C RELATED SPECIFICATIONS
• Emergency shutdown valves
• Instrumentation for skid-packaged equipment
• Design specifications: process design of flare and blowdown systems, pressure control and OPP guidelines, isolation standard

FACILITY PIPING SPECIFICATIONS
• Piping tables for B31.3, CSA B149.1, CSA Z662
• Services: sweet, sour, cryogenic, corrosive, fuel gas distribution system, liquid sulphur, utility, heating fluids, lubricants/hydraulic fluids
• Materials: carbon steel, stainless steel
• Manual valves
Stainless steel tubing

OTHER SPECIFICATIONS AND STANDARDS
• Pressure welding (piping & equipment)
• Pig closure replacement procedure
• Bolting, gaskets and torquing
• Induction bends from steel pipe

Domestic Project Highlights

Domestic Project Highlights
Acero has a diverse project portfolio which includes tight budget and schedule field-operations-driven MOC projects, numerous green/brown field facility projects ranging in size/complexity, CPFs, stand-alone gas plant projects and numerous pipeline projects. Acero has completed over 2500 well tie-ins and associated gathering systems, oil and gas facility upgrades and can easily facilitate projects up to $100MM TIC.

MAJOR PROJECTS
Client Location Year Project Description
Baytex Energy Corp. Various 2008 – Ongoing Field Development Programs  Participated in over 300 projects ranging in size and complexity throughout Peace River, Lloydminster, Duverney.  
Painted Pony Energy Ltd. Fort St. John, BC 2013 – Ongoing Field Development Projects  Well Pad Equipment Projects, Gas Plant Debottleneck & Expansion
Confidential Client Judy Creek, AB 2018 – Ongoing Pipeline Replacements 3″ & 4″ FRP HP Produced Water Injection Pipelines, 3″ & 4″ FRP Flowline Replacements, 8″ FRM Groupline Replacements
Confidential Client Kaybob/South Swann Hills/Virginia Hills 2018 – Ongoing Engineering General Support Engineering Support for Carson Creek Gas Plant, Judy Creek Gas Plant
Canadian Natural Resources Ltd (CNRL) Septimis, Ferrier 2017 – Ongoing Multi-Well Pad & Pipeline Projects Multi-Well Pad & Pipeline installations including acid gas pipeline from Stoddart gas plant
Various Various 2017 – Ongoing Specification Development for E&P Facilities & Pipelines In-house mechanical specs for Domestic & International energy companies
Confidential Client Various 2019 Methane Emissions Site visit to validate whether or not they need a methane reduction retrofit compliance plan (MRRCP)
Confidential Client Fort St. John, BC 2019 Parkland Water Injection  Designed to handle 300m3/d with ability to expand to 600 m3/d
Painted Pony Energy Ltd. Fort St. John, BC 2019 Daiber Compressor Station Designed for 50 MMSCFD of high press production and 25 MMSCFD of low pressure compression
Razor Energy Corp. Swan Hills, AB 2019 Power Generation Evaluation of (2) power generation scenarios
Confidential Client Red Deer, AB 2018 – 2019 Gilby Central Oil Battery  4,0000 BBL/D Light oil, and 5 MMSCFD gas
Confidential Client Grande Prairie, AB 2018 Amine Installations Amine plants will have a gas max throughput of 60 MMSCFD, and amine circulation rate of 60 GPM (each)
Confidential Client Fort St. John, BC 2018 McMahon Gas Plant Amine Still Replacement  Amine Still replacement with 316L stainless steel
Confidential Client Central AB 2018 Ferrier Gas Plant & Debottlenecking Pre-FEED to increase throughput from 6 to 13 MMSCFD and 1,200 to 2,000 bpd of condensate
Confidential Client Edson, AB 2018 Pine Creek Compressor Station FEED Designed to handle 20-25 MMSCFD of gas with maximum liquid yield of 100bbl/MMSCFD
Baytex Energy Corp. Soda Lake, SK 2018 Soda Lake Water flood Expansion Pipeline and facility engineering to expand water flood operation, with consideration to become polymer flood in future operations.
Confidential Client Various 2018 Asset Circutization Support Circutization and asset verification of 70 sites
Confidential Client Central AB 2017-2018 Power Generation 16 MW power at give locations to reduce reliance on utility power
Confidential Client Fort St. John, BC 2017-2018 B-24-H Sour Gas Plant Debottleneck Expansion Expansion from 22 MMSCFD to 40 MMSCFD
Pengrowth Energy Corp Montney Field, BC 2017 Pipeline Network Modeling  Network contained (17) wells, (7) pipeline segments
Pengrowth Energy Corp Irricana, AB 2017 Pipeline Network Modeling  Network contained (20) wells, (42) pipeline segments, and (1) booster compressor
Confidential Client Laprise Creek, BC 2017 Water Hub Pipelines (5) Bi-directional pipelines from CPF to water storage facility
Confidential Client Central AB 2017 Wilrich Compressor Station Expansion Addition of 48 MMSCFD train in parallel with existing 22 MMSCFD facility; resulting in total plant throughput of 60 MMSCFD
Confidential Client Edson, AB 2017 Edson Gas Plant Water Offload Truck-In  Facility upgrade to allow for 100m3/d produced water
Polar Star Canadian Oil and Gas Inc. Laprise Creek, BC 2017 Pipeline Projects  10″ – 12 km main trunk line /w several crossing considerations
Pengrowth Energy Corp Swan Hills, AB 2014-2017 Fugitive Emission Evaluation  Wellsite and facility fugitive emission calculations to re-classify process buildings as necessary to reduce equipment costs
Pengrowth Energy Corp Judy Creek, AB 2016-2017 Tank Replacements  Replacement and relocation of three tanks
Painted Pony Energy Ltd. Townsend, BC 2016-2017 Dual 12” Pipelines  Dual NPS 12” pipelines; 2,700m in length between existing risers
Painted Pony Energy Ltd. Fort St. John, BC 2016 Gas Plant Debottleneck & Expansion Expansion from 28 MMSCFD to 40 MMSCFD
Pengrowth Energy Corp. Carson Creek, AB 2015-2016 Carson Creek Tank Installation  15,000 bbl produced water storage tank, and 10″ flare
Pengrowth Energy Corp. Southern AB 2015 Custom Flow Splitter  Process sizing, selection, skid design, and integration of custom packaged pipeline flow splitter
Pengrowth Energy Corp. Southern AB 2015 Garrington Glycol Dehy Installation  Glycol Dehy into existing facility to allow for increased production
Pengrowth Energy Corp Southern AB 2015 Garrington Pipeline Installations New pipeline to re-route field production
Crew Energy Inc. Fort St. John, BC 2013-2015 Septimus Gas Plant Expansion – Sour Expansion from 20 MMSCFD sour gas inlet refrigeration and LPG extraction plant, and expansion to 40 MMSCFD
Cabot Energy Zama Lake, AB 2014 Field Development Projects  Field Development Projects such as greenfield single well batteries, pipeline installations and reactivations, oil effluence gathering systems
Baytex Energy Corp. Peace River, AB 2014 Water Disposal Facility Expansion of existing oil battery to incorporate water handling.  Installation of (3) 2000 bbl water tanks
Madalena Energy Inc. Paddle River, AB 2011-2014 Field Development Projects  Multiple oil batteries, well tie-ins, and various pipeline projects
Pengrowth Energy Corp. Central AB 2013 Lochend Battery Booster Compressor Expansion to inscrease throughput from 18 MMSCFD to 23 MMSCFD of raw gas by upsizing dehydrator and installing booser compressor
Pengrowth Energy Corp. Southern AB 2013 Jenner SKUD Addition of SKUD, booster pumps, & injection pump to increase water handling capacity at existing battery
Pengrowth Energy Corp. Judy Creek, AB 2013 Water Injection Facility & Pipeline  Water Injection Facility & Pipeline 
Pengrowth Energy Corp. Swan Hills, AB 2013 Gas Pipeline Replacements  Multiple 4″ to 12″ LP & HP gas pipeline replacements
Pengrowth Energy Corp. Judy Creek, AB 2013 Booster Pump Installation  Water injection capacity of 16,000 m3/d at 14,900 kPag
Crew Energy Inc. Fort St. John, BC 2010 Septimus Gas Plant Gas Plant Phase 1 – 22 MMSCFD
Baytex Energy Corp. Fort St. John, BC 2012 Cache 3-24 Satellite and Tie-In  5 MMSCFD sour gas single well battery/w natural gas and fuel gas pipelines to/from existing 10-20 compressor station
MOC WORK
Confidential Client Various 2018 – Ongoing Pipeline Integrity Repairs, Sectional Replacements, & Rerouting of pipelines between 8″ to 22″
Razor Energy Corp. Central AB 2018 Facility & Pipeline Engineering Support General Support, evaluation of MOCs, scoping small projects throughout Virginia Hills Oil Battery, Kaybob, & Swan Hills Operations
Confidential Client NE BC 2017-2018 Commissioning Support  Pine River, McMahon, Fort Nelson Gas Plant Turnaround Commissioning & Construction Support
Pengrowth Energy Corp Judy Creek, AB / Deer Mountain, AB 2017 Pipeline Replacements Pipeline Replacements
Confidential Client Fort Nelson, BC 2017 Flare System Revamp  Flare System revamp at Fort Nelson Gas Plant.
Confidential Client Pounce, AB 2015 Progress Venturi VRU Flare and VRU system revamp
Confidential Client Fox Creek, AB 2014 Fox Creek Brownfield Upgrades  Field driven time and cost sensitive projects
Pengrowth Energy Corp. Swan Hills, AB 2013 Gas Pipeline Replacements  Multiple 4″ to 12″ LP & HP gas pipeline replacements
Pengrowth Energy Corp. Swan Hills, AB 2012 TEG Contactor Equipment Upgrade  Replacement glycol contactor and new condensate coalescer and filter

CLICK HERE TO DOWNLOAD our Domestic Project Highlights Brochure

International Project Highlights

International Project Highlights
Acero has successfully completed over 50 conceptual, Pre-FEED, FEED, Detailed Engineering and Construction Support Projects in Iraq, Egypt, Chad, Sudan, India, Russia and South America. Our extensive experience with full scopes of project work, from concept through detailed engineering and construction management, allows Acero to examine the feasibility of various options and work with our clients to select a ‘best path forward’ for development.

MAJOR PROJECTS
Client Location Year Project Description
Gran Tierra Energy Inc. Colombia 2019 Gas Injection at AC-2 Gas injection for 5 MMSCFD
Gran Tierra Energy Inc. Colombia 2019 Gas Injection at AC-4 Gas injection for 5 MMSCFD
Gran Tierra Energy Inc. Colombia 2018-19 Standard Modular EPF Modular EPF design (30k BOPD)
PCM, a Glencore Company Chad 2018-19 Mangara Well Tie-in Program Multi wellpads c/w flowlines
PCM, a Glencore Company Chad 2018-19 Badila Well Tie-in Program Multi wellpad c/w flowline
Gran Tierra Energy Inc. Colombia 2017-19 Putumayo Mobile Testing Facility Extended well testing facility 3,000 BOPD
Gran Tierra Energy Inc. Colombia 2017 Acordionero CPF Expansion Phase 1 CPF expansion from 3500 BOPD to 7500 BOPD
Gran Tierra Energy Inc. Colombia 2017 Acordionero CPF Expansion Phase 2 CPF expansion from 7500 BOPD to 45000 BFPD
Gran Tierra Energy Inc. Colombia 2017 Acordionero Power Generation Power generation 14 MW c/w Grid to feed CPF and 6 multiwell pads
Gran Tierra Energy Inc. Colombia 2017 Acordionero Water Injection Water Injection Facility 30,000 BWPD
Gran Tierra Energy Inc. Colombia 2017 Acordionero CPF Truck Loading Facility Truck loading Facility 30,000 BPD
Gran Tierra Energy Inc. Colombia 2017-19 Blending Facility and Crude Oil Export P/L Blending Terminal and export P/L (20,000 BPD)
Odin Petroil Colombia 2016 Odin Petroil Distillation Facility Upgrading of distillation facility 950 BPD to 1,800 BPD
PCM, a Glencore Company Chad 2015 Badila Power Generation Power generation 9 MW c/w Grid to feed 31 wells, Water injection Facility and Camp
Griffiths, a Glencore Company Chad 2015 Crude Oil Topping Unit Conceptual Study for a crude oil topping unit on the Kibea P/L
PCM, a Glencore Company Chad 2015 PCT Blending and Export Terminal Expansion Expansion of the Blending and Export Terminal from 35k BPD to 75k BPD
PCM, a Glencore Company Chad 2015 Mangara Power Generation Power generation 6 MW c/w Grid to feed 41 wells
PCM, a Glencore Company Chad 2015 Badila Satellite 2 Satellite 7,000 BPD to handle 10 Wells
PCM, a Glencore Company Chad 2014 Badila Water Injection Water Injection Facility 65,000 BWPD
PCM, a Glencore Company Chad 2014 Badila Gas Injection Gas Injection Facility 12.4 MMSCFD
Gran Tierra Energy Inc. Peru 2014 Bretana Development – 20,000 BPD EPF EPF 20,000 BOPD
Confidential Client Kurdistan 2014 Summail Gas Train 2 140 MMSCFD Gas plant c/w Amine and Dehy contactor
Confidential Client Kurdistan 2014 ENI Zubair O&MSF OMSF 40,000 BOPD
Confidential Client Kurdistan 2014 EPF 10,000 BPD EPF 10,000 BPD
Confidential Client Kurdistan 2014 EPF 10,000 BPD EPF 10,000 BPD
Confidential Client Kurdistan 2013 Kuradmir Block Development CPF 50,000 BOPD and 200 MMSCFD (c/w sulfur recovery plant)
Confidential Client Kurdistan 2013 Talisman K2  5,000 BOPD EWTF EPF 5,000 BOPD (42 API and 4,000 GOR)
Confidential Client Kurdistan 2013 Talisman K3  5,000 Modified Testing Facility EPF 5,000 BOPD
Confidential Client Kurdistan 2013 OS Standard EPF Standard design for EPF 5,000 BOPD
Confidential Client Kurdistan 2013 Genel Miran EWT EPF 5,000 BOPD (14 API & 75% WC)
Confidential Client Kurdistan 2012 HKN ST-1    5,000 BOPD EPF EPF 5,000 BOPD (29 API)
Canoro Resources Ltd. India 2011 Amguri Inerim Condensate Recovery 20 MMSCFD gas plant and 1,500 bpd condensate recovery
Centurion Energy International Inc. Egypt 2011 El Wastani Inlet Modifications Gas Plant Optimization & De-Propanizer Addition
Zedi Inc. Russia 2011 Silver Jack Hydraulic Lift Silver Jack Hydraulic Lift
MOC WORK
PCM, a Glencore Company Chad 2019 Camp Accomodation Upgrade – Mangara Expansion of Mangara Camp
PCM, a Glencore Company Chad 2019 Camp Accomodation Upgrade – Badila Expansion of Badila Camp
PCM, a Glencore Company Chad 2019 Adding of Pig Launchers and Receivers Mangara – Badila Pipeline
Gran Tierra Energy Inc. Colombia 2019 Water Injection Pump Skid TBD

 

International Project Highlights Brochure CLICK HERE TO DOWNLOAD

Calgary

Headquarters

Suite 900, 600 6 Ave SW
Calgary, AB
Canada T2P 0S5

+1 403-237-7388

admin@aceroeng.com

Location

Find Us

Get In Touch

Contact Us

12 + 5 =