PROJECT: Booster Pump Installation COMPANY: Pengrowth Energy Corp. LOCATION: Judy Creek, AB
Acero was responsible for the detailed engineering and design, procurement of main equipment and construction support of a pump station in central Alberta. The project featured two 750 HP pumps and housings to provide water injection capacity of 16,000 m3/d at 14,900 kPag.
PROJECT: NEBC Midpoint Pump Station FEED COMPANY: Confidential Client LOCATION: NE BC
Acero was responsible for FEED study to construct a mid-point pump station to support increased volumes (C3+ & C5+) on the line using a 5,000 HP pump. Scope of work included the necessary drawings, philosophy, TIC cost estimate, and associated deliverables to complete the FEED.
PROJECT: Kaybob Site Upgrades COMPANY: Pembina Pipeline Corp. LOCATION: Kaybob
Acero was responsible for the FEED, detailed engineering and procurement for the upgrades to the 03-29 Kaybob site which consisted of a tank farm with a booster pump and a shipping pump station. The scope of work included the replacement of the BS&W analyzer, sump tank, Electrical building, controls, and upgrading the OPP on shipping pumps.
PROJECT: North Inga Crude LACT FEED COMPANY: Confidential Client LOCATION: NE BC
Acero was responsible for the engineering and procurement to connect ConocoPhillips’ North Inga Gas Plant to the to start of Pembina’s Blueberry mainline; using two multistage horizontal centrifugal pumps of 500 HP each. The LACT facility was designed to handle 11,000 BPD at a discharge pressure of 6900 kPag.
PROJECT: Nig Creek C5+ LACT FEED COMPANY: Confidential Client LOCATION: NE BC
Acero was responsible for the engineering and procurement to connect Black Swan Energy Aitken Gas Plant to the Pembina Town Terminal. The product was shipped using a 300 HP multistage horizontal centrifugal pump. The LACT facility was designed to handle 50 m3/h at a discharge pressure of 6900 kPag.
The Saturn LACT facility is comprised of two LACT skids. Acero’s scope of work included the FEED and detailed engineering, procurement, and construction management of the below modifications:
Installation of a pump sleeve casing drain and vent piping to allow for water removal and antifreeze injection
Piping modifications and installation of DIB-2 valves associated with Saturn 1 & 2 LACT meters and prover
Re-build and installation of discharge piping
Repair of damaged structural steel on pump skid, and the rotation of the pump motors to improve maintenance access
INTERNATIONAL
PROJECT: Crude Oil Topping Unit COMPANY: Griffiths, a Glencore Company LOCATION: Chad, Africa
Acero was responsible for the conceptual study to evaluate the feasibility of installing a crude oil topping at the initial pumping station of a 16”, 520 km pipeline. Pipeline hydraulic simulations were also provided to analyze options for pump and heating stations, variations in MAOP, production capacities, and pipeline sizes, based on crude oil assay and temperature.
PROJECT: PCT Blending & Export Terminal Expansion COMPANY: PCM, a Glencore Company LOCATION: Chad, Africa
As part of the expansion of the PCT Export facility Acero was responsible for increasing the capacity of the pumping station including harmonics study and the upsizing of the LACT unit to accommodate the increase in the flowrates.
Acero Engineering is a leading provider of comprehensive engineering, procurement, and construction management (EPCM/EPC) solutions. With expertise in designing and executing projects for gas processing facilities, compressor stations, and oil processing, our team ensures efficient pipeline operations and the management of change (MOC). We specialize in pipeline and piping integrity, pump and truck loading stations, LACTS, oil terminals, and regulatory compliance. From oil and produced water storage to acid gas injection and carbon storage, we deliver tailored solutions and adhere to the highest industry specifications.